Triview reports $107,844 cost to draw down South Reservoir and remove pump
The pump has been removed and is being evaluated to determine why it failed and estimate repair costs.
Published at
Triview Metropolitan District reported $107,844.12 in cumulative costs to draw down South Reservoir and remove its discharge pump, which became stuck in its pipe, in a Nov. 19 utility report included in the board packet.
Crews drew down the reservoir to reach the pump. Removing it required cutting off and removing the top half of the pipe. The pump has been removed, and DXP is evaluating it to determine the cause of the failure and estimate repair costs, the report said. The reported total excludes some water-operations staff time.