Draft puts Manitou Springs’ Lovers Lane wall rebuild at $2.93 million

An unsigned construction amendment proposes a $2.34 million construction price, targets substantial completion by May 28, 2027, and assumes a full road closure during major wall work.

An “As Constructed” engineering sheet for Lovers Lane shows two retaining-wall sections.
An “As Constructed” engineering sheet for Lovers Lane shows two retaining-wall sections.

Published at

An unsigned construction amendment for Manitou Springs’ Lovers Lane retaining-wall rebuild puts the proposed total project cost at $2.93 million, up from an earlier estimate of about $2.4 million. The draft targets substantial completion by May 28, 2027.

The Nov. 13 draft amendment and cost summary list a proposed guaranteed maximum construction price of $2,338,536.19 and a total project cost of $2,930,651.19. The draft is unsigned, and the City Council’s Nov. 17 meeting packet lists the Lovers Lane contract items for consideration; neither establishes that the City approved or executed the terms. The draft says the start date would be set through the City’s written Notice to Proceed, and that the price is based on 90% design documents. Material scope or design changes could require a contract modification.

The City had announced a planned Nov. 15 construction start and said portions of Lovers Lane would close during the work. The draft assumes the road will be fully closed during major wall operations and that a temporary bypass will maintain downstream creek flow during winter low-flow conditions. Those are planning assumptions, not a final traffic-control plan; the draft does not set closure dates or duration.

A June Pikes Peak Rural Transportation Authority board packet described a $92,000 preconstruction contract for Myers & Sons Construction and said the negotiated construction amount would return for approval. The packet cited an earlier project estimate of about $2.4 million. The City retains ownership and responsibility for the project, while the authority is a funding partner.

A March City Council report put the project cost at roughly $2.4 million and said there would be no city cost share. The authority authorized advancing up to $2.4 million in capital funds for the work; that authorization was not a construction contract or award.

City staff have described the wall as failing quickly. Draft historic-review materials warn that continued deterioration could lead to roadway failure toward Fountain Creek and damage or loss of nearby utilities. The proposed work would replace the wall in kind, matching its concrete material, color, appearance, height, length, alignment and footprint. It also includes drainage scuppers and a separate safety rail; the engineering drawings specify a bridge-rail design with crash-performance criteria.

A staff memo in the Nov. 4 Historic Preservation Commission agenda packet described continuing federal historic-preservation review involving the U.S. Army Corps of Engineers, while the Colorado State Historic Preservation Office considers whether the wall is eligible for the National Register of Historic Places. The memo also proposed a commission support letter; it does not establish a final City or agency determination.

Temporary repairs to the wall were completed in April 2025, according to a City report to the transportation authority.