El Paso County approves nearly $2 million for Highway 105 utility trench
The county approved a construction contract capped at $1.77 million and a $221,205 task order for construction management, inspections and testing.
Published at
El Paso County commissioners approved nearly $2 million in contracts for a utility trench along Highway 105, which will let telecommunications providers move lines ahead of a future road widening.
The commissioners approved the contracts unanimously as part of the consent calendar Nov. 17, the county’s minutes show. The county awarded RJ Gleeson Construction a contract capped at $1,765,894 and Vivid Engineering Group a $221,205 task order for construction management, inspections and materials testing. The awards total $1,987,099; the construction contract’s maximum is not money already spent.
The trench will run along the highway’s north shoulder from Lake Woodmoor Drive to Martingale Road. The county’s project description says the trench will give telecommunications providers a place to relocate lines that conflict with a future widening and reconstruction project. The procurement documents identify fiber-optic, cable television and telephone facilities for removal, relocation, splicing or abandonment.
The solicitation names Comcast Cable, Lumen Technologies, Verizon/MCI, Stratus IQ, Segra and Force Broadband among the participating telecommunications owners, and says the county will own the trench, according to the solicitation.
The awards are funded through the Pikes Peak Rural Transportation Authority. The county listed no net cost to its budget for either contract.
The county project page anticipated the first phase would begin in December 2026 or January 2027. It said two-way traffic would be maintained as much as possible, with single-lane closures and flaggers as needed.