Manitou Springs draft budget proposes $23 stormwater fee, $6.1 million for street projects
The proposal would charge water and sewer utility accounts monthly and fund street, drainage and pedestrian work, plus a proposed $1.915 million allocation for Lovers Lane; the Nov. 16 work session was for discussion, not decisions.

Published at
Manitou Springs’ proposed 2027 budget would charge $23 a month per water and sewer utility account for stormwater services and allocate more than $6.1 million for two street projects, including work on Ruxton Avenue and East Manitou Avenue.
The proposed assessment would support the city’s federally required stormwater-monitoring program, drainage-system improvements, capital work and debt service, the city administrator’s budget message says.
The budget lists $5,490,657 for the Ruxton project and $620,000 for East Manitou Avenue pedestrian and drainage improvements in 2027. The East Manitou work is part of a two-year project estimated at $2.62 million, with another $2 million planned for 2028. The project would improve storm drainage, sidewalks and access for people walking and using other modes near the Highway 24 exit and Dillon Mobility Hub, according to the city’s capital plan.
The proposal also includes $1.915 million for Lovers Lane Permanent Creek Wall through the Pikes Peak Regional Transportation Authority (PPRTA) Public Facilities Fund. The city describes the allocation as capital for its road system dedicated to Lovers Lane needs; the amount includes an advance allocation from 2028 and 2029. It is a proposed budget allocation, not a contract award, the work-session packet says.
The Ruxton project covers about 3,400 feet and includes street resurfacing, curb and sidewalk replacement, accessibility and multimodal improvements, designated parking, storm-sewer work, sanitary-sewer rehabilitation and water-system upgrades. In 2027, staff plan to continue design, floodplain permitting and right-of-way work; construction is not expected before 2028, a November staff update says.
The proposals were presented at the City Council’s Nov. 16 budget work session, which was designated for discussion and direction, not decisions. The packet presents the budget as proposed, not adopted.
The capital and drainage proposals are separate from operating reductions outlined in an October staff memo, which discussed proposed cuts to ongoing city spending and reductions already implemented, the memo says.